CONSTRUCTION UPDATE – October 19, 2018
Crews will be performing the following work along US-89:
-
Striping will continue to be applied throughout the next week.
-
Installation of drainage pipes along US-89 will be completed on Monday, October 22.
-
Shouldering will be completed on Monday, October 22, and cleanup will last through Wednesday, October 24.
-
Curbs will be installed Thursday, October 25, through Friday, October 26.
-
Work on guardrails and barricades will be worked on all of next week and into the following week.
Please prepare for intermittent lane closures on US-89 as striping in completed. All work is weather dependent.