CONSTRUCTION UPDATE – SEPTEMBER 24, 2018
During this week, crews will be performing the following work along US-89:
-
Paving on SR-126 will begin on Tuesday, September 25, focusing on the ramps and part of the bridge. The southbound ramp will be unavailable temporarily during this time, with a detour available for use.
-
Paving on US-89 will begin on Wednesday, September 26. Paving will begin on the north end of the project and move south.
-
Three pedestrian ramps will be installed on 7615 South and 200 South on Monday, September 24.
-
Excavation for widening on 750 North will begin as early as Monday September 24.
-
Crews will continue to install infrastructure for the signal at 750 North.
As part of construction, businesses, residents, and motorists should expect intermittent lane and shoulder closures along US-89, 750 North, and the ramps along US-89.