CONSTRUCTION UPDATE – SEPTEMBER 24, 2018
During this week, crews will be performing the following work along US-89:

  1. Paving on SR-126 will begin on Tuesday, September 25, focusing on the ramps and part of the bridge.  The southbound ramp will be unavailable temporarily during this time, with a detour available for use.
  2. Paving on US-89 will begin on Wednesday, September 26. Paving will begin on the north end of the project and move south.
  3. Three pedestrian ramps will be installed on 7615 South and 200 South on Monday, September 24.
  4. Excavation for widening on 750 North will begin as early as Monday September 24.
  5. Crews will continue to install infrastructure for the signal at 750 North.

As part of construction, businesses, residents, and motorists should expect intermittent lane and shoulder closures along US-89, 750 North, and the ramps along US-89.

 

 