CONSTRUCTION UPDATE – November 5, 2018
Crews will perform the following work along US-89 and 750 N:

  1. Work on the traffic signal at 750 North begin on Monday, November 5 and last through the following week.
  2. Grinding of the roadway will begin on Wednesday, November 7.  Please be prepared for short lane closures during this process.
  3. A barrier on 750 N will be installed Monday, November 5 and Tuesday, November 6.