US 89 Shoulders Project Update 27

Sunday, September 24, 2017 - 1:45pm
UDOT

US 89 Shoulders Project - September 21, 2017

 

Current Work

▪ Crews have completed shoulder paving between Blazer Plastics and 8200 South.
▪ Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.

Crews have completed shoulder paving between Blazer Plastics and 8200 South.

Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.

Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.

Current Closures

▪ The right lane for northbound traffic is closed while crews work on shoulder reconstruction.

The right lane for northbound traffic is closed while crews work on shoulder reconstruction.

 

Upcoming Work

▪ Once paving is complete road paint and signs will be placed.
▪ Work in front of Pettingills is expected to begin in a few weeks.

Once paving is complete road paint and signs will be placed.

Work in front of Pettingills is expected to begin in a few weeks.

 

Project Location

UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.

Purpose of the Project

This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.

What to Expect

▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete the end of October 2017.

Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.

Anticipate construction noise and vibrations.

The right travel lane will be closed in the areas in which crews are working.

This project is expected to be complete the end of October 2017.

 