▪ Crews have completed shoulder paving between Blazer Plastics and 8200 South.
▪ Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.
▪
Crews have completed shoulder paving between Blazer Plastics and 8200 South.
▪
Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.
▪
Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.
▪ The right lane for northbound traffic is closed while crews work on shoulder reconstruction.
▪
The right lane for northbound traffic is closed while crews work on shoulder reconstruction.
▪ Once paving is complete road paint and signs will be placed.
▪ Work in front of Pettingills is expected to begin in a few weeks.
▪
Once paving is complete road paint and signs will be placed.
▪
Work in front of Pettingills is expected to begin in a few weeks.
UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.
This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.
▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete the end of October 2017.
▪
Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪
Anticipate construction noise and vibrations.
▪
The right travel lane will be closed in the areas in which crews are working.
▪
This project is expected to be complete the end of October 2017.