Error message

US 89 Shoulders Project Update 17

Friday, July 7, 2017 - 11:30am
UDOT

US 89 Shoulders Project - July 5, 2017

 

Current Work

▪  Crews anticipate beginning shoulder work on the east side of the road on July 10.
▪ Gas line tie-ins from the east side of the road to the west side are underway.
▪ Crews are continuing to place traffic signs on the west side of the road. Southbound lane restrictions will remain in place during this work.

Crews anticipate beginning shoulder work on the east side of the road on July 10.

Gas line tie-ins from the east side of the road to the west side are underway.

Crews are continuing to place traffic signs on the west side of the road. Southbound lane restrictions will remain in place during this work.

Please do not move traffic control barrels or cones. These are placed in specific areas to insure the safety of motorists, residents, and construction workers.

Current Closures

▪ Temporary lane closures in the northbound right travel lane are expected over the next few weeks. This will be to accommodate the work that Questar is doing on the current gas line.

Temporary lane closures in the northbound right travel lane are expected over the next few weeks. This will be to accommodate the work that Questar is doing on the current gas line.

 

Upcoming Work

▪  Crews anticipate beginning shoulder work on the east side of the road on July 10.

Crews anticipate beginning shoulder work on the east side of the road on July 10.

 

Project Location

UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.

Purpose of the Project

This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.

What to Expect

▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete around Labor Day weekend 2017.

Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.

Anticipate construction noise and vibrations.

The right travel lane will be closed in the areas in which crews are working.

This project is expected to be complete around Labor Day weekend 2017.

 

Tags: